1990 - 1. Nuclear Power Plant
                (Pipe)

Period
Project
Customer
Feb. 1992 - Aug. 1992 PWHT for the main facilities Pipe at #3, #4 unit YoungKwang Nuclear Power Plant Hanjung. Corp.
Feb. 1992 - Apr. 1995 Pre-Heating, PWHT for the main facilities Pipe at #3, #4 unit YoungKwang Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.
May. 1994 - Apr. 1996 PWHT for the main facilities Pipe at #2 unit WolSung Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.
Dec. 1995 - Dec. 1998 Pre-Heating, PWHT for the main facilities Pipe at #3, #4 unit WolSung Nuclear Power Plant DaeWoo Eng. & Const. Co., Ltd.
Dec. 1995 - Dec. 1997 Pre-Heating, PWHT for the main facilities Pipe at #3, #4 unit UlJin Nuclear Power Plant DongA Eng. & Const. Co., Ltd.
Mar. 1998 - Dec. 1998 Pre-Heating, PWHT for the Steam pipes, Water pipes under replacing job for the Steam Generator at #1 unit KoRi Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.
Oct. 1998 - Dec. 2002 Pre-Heating, PWHT for the main facilities Pipe at #5, #6 unit YoungKwang Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.

1990 - 2. Nuclear Power Plant
                (Pressure Vessel and Structures)

Period
Project
Customer
Dec. 1990 - Dec. 1991 Pre-Heating, PWHT for the Steam Generator, Reactor Vessels at #3, #4 unit YoungKwang Nuclear Power Plant Hanjung Corp.
Jun. 1991 - Aug. 1991 PWHT for the #4 the turbine generator building at #3, #4 unit YoungKwang Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.
Jun. 1991 - Nov. 1991 Pre-Heating, PWHT for the steam generator final vessel at #3, #4 unit YoungKwang Nuclear Power Hanjung Corp.
Apr. 1992 - Jun. 1992 PWHT for the support column and cold leg pipe at #3, #4 unit YoungKwang Nuclear Power Plant
Hanjung Corp.
May. 1992 - May. 1992 PWHT for the turbine generator upper casing at #3, #4 unit YoungKwang Nuclear Power Plant Hanjung Corp.
Nov. 1992 - Dec. 1992 PWHT for #3 unit FB building at YoungKwang Nuclear Power Plant HyunDai Eng. & Const. Co., Ltd.
Jan. 1993 - Jan. 1993 Pre-Heating, PWHT for the turbine generator at #3, #4 unit YoungKwang Nuclear Power Plant Hanjung Corp.
Feb. 1993 - Mar. 1993 PWHT for the stack at #3, #4 unit YoungKwang Nuclear Power Plant PWHT HyunDai Eng. & Const. Co., Ltd.
May. 1993 - May. 1995 Pre-Heating, PWHT for the Steam Generator and other 2types at #3, #4 unit UlJin Nuclear Power Plant Hanjung Corp.
Aug. 1993 - Jul. 1996 Pre-Heating, PWHT for the Steam Generator at #2, #3, #4 unit WolSung Nuclear Power Plant Hanjung Corp.
Jul. 1996 - Dec. 1997 Pre-Heating, PWHT for #1 unit the steam generator at KoRi Nuclear Power Plant Hanjung Corp.
Mar. 1997 - Sep. 1999 Pre-Heating, PWHT for the #5, #6 unit steam generator and other Nuclear Vessel at YoungKwang Nuclear Power Plant Hanjung Corp.
May. 1999 - Sep. 2002 Pre-Heating, PWHT for the #1, #2 unit NSSS lower vessel assembly  at JinSan Nuclear Power Plant Hanjung Corp.
Oct. 1999 - Nov. 2002 Pre-Heating, PWHT for #5, #6 unit the steam generator and other Nuclear Vessel at UlJin Nuclear Power Plant DooSan Heavy Ind. Co., Ltd.

1990 - 3. The Thermal power plant and other power plant

Period
Project
Customer
Feb. 1988 – Jul. 1990 Pre-Heating for the hydraulic pipe at KangReung Water Power Plant Hanjung Corp.
Dec. 1991 - Feb. 1992 PWHT for #5 unit the boiler integral pipe at BoRyeong Thermal power plant Hanjung Corp.
Feb. 1992 - Feb. 1994 Pre-Heating for the hydraulic pipe at MuJu Water power plant Hanjung Corp.
Jun. 1992 - Jun. 1993 PWHT for #1, #2 unit the boiler header at TaiAn Thermal Power Plant Hanjung Corp.
Jan. 1995 - Mar. 2001 PWHT for #1, #2, #3, #4, #5 unit the pipe at HaDong Thermal Power Plant Hanjung Corp.
Dec. 1997 - Jun. 1999 PWHT for #1, #2 unit the boiler and turbine pipe at DangJin Thermal Power Plant DongA Eng. & Const. Co., Ltd.
Aug. 1998 - Sep. 1999 PWHT for the pipe in 3rd stage construction job at KwangYang Combined Cycle Power Plant POSCO development Co., Ltd.
Dec. 1998 - Oct. 1999 Pre-Heating for the hydraulic pipe at SanChung Water power plant DongA Eng. & Const. Co., Ltd.
Mar. 1999 - Mar. 2001 PWHT for #4 unit the boiler, turbine pipe at DangJin Thermal Power Plant DongA Eng. & Const. Co., Ltd.
Dec. 1999 - Feb. 2001 PWHT for the pipe in LNG power generation facilities 3rd stage construction job at PoHang POSCO development Co., Ltd.
Dec. 1999 - Apr. 2002 PWHT for #5, #6 unit the boiler, T/G pipe at TaiAn Thermal Power Plant LG Eng. & Const. Co., Ltd.

1990 - 4. Oil Refinery and Petrochemical plant

Period
Project
Customer
Aug. 1989 - Jun. 1990 PWHT for Aromatic Compound manufacturing plant pipe at YeoSu Oil Refinery Plant of LG-Caltex. LG-Caltex Corp.
Jan. 1990 - Feb. 1990 PWHT for the pipe in YeoSu PE plant of LG Chem. LG Develop. Co., Ltd.
Feb. 1990 - Apr. 1991

PWHT for the pipe in Power facilities increase construction at UlSan Oil Refinery Plant of SK Corp.

SK Eng. & Const. Co., Ltd.

Mar. 1990 - Jun. 1990

PWHT for the P/A field Pipe in YeoSu plant of KumHo Shell Corp.

KumHo Shell Corp.

May. 1990 - Sep. 1991

Pre-Heating, PWHT for the pipe in LPC-NC project at YeoSu Plant of LG Petrochemical.

LG PetroChemical Co., Ltd.

Jun. 1990 - Jun. 1990

PWHT for the desalter pipe at YeoSu Oil Refinery Plant of LG-Caltex.

LG-Caltex Corp.

Oct. 1990 - Oct. 1990

PWHT for the pipe in the manufacturing construction at NamHae Chemical.

SK Eng. & Const. Co., Ltd.

Oct. 1990 - Mar. 1991

PWHT for the convection coil at YeoSu plant of HoNam Petrochemical.

HanKook Fertilizer Co., Ltd.

Nov. 1990 - Dec. 1991

Pre-Heating, PWHT for the pipe in Increase construction at InCheon Oil Refinery Plant of KyungIn Energy.

DaeLim Ind. Co., Ltd.

Dec. 1990 - Jan. 1991

PWHT for the S/D pipe in YeoSu Plant of HoNam Ethylene.

HoNam Ethylene Corp.

Dec. 1990 - Apr. 1991

PWHT for the pipe at DaeSan Plant of HyunDai Petrochemical Co.

HyunDai Eng. & Const. Co., Ltd.

Mar. 1991 - Jun. 1991

PWHT for the steam line at UlSan Oil Refinery Plant of SK Corp.

SK Eng. & Const. Co., Ltd.

May. 1991 - Dec. 1991

PWHT for the pipe in GO HDS project (Light Oil desulfurized project) at YeoSu Oil Refinery Plant of LG-Caltex.

LG-Caltex Corp.

May. 1991 - Feb. 1992

PWHT for HOU IBL #7unit the BL pipe at UlSan Oil Refinery Plant of SK Corp.

SK Eng. & Const. Co., Ltd.

Aug. 1991 - Jan. 1992

PWHT HOU OBL pipe at UlSan Oil Refinery Plant of SK Corp

SK Eng. & Const. Co., Ltd.

Oct. 1991 - Mar. 1992

PWHT for NCC pipe at YeoSu plant of HanYang Chem.

SamSung Eng. & Const. Co., Ltd.

Feb. 1992 – Jul. 1992

Pre-Heating, PWHT for BTX pipe at YeoSu plant of LG Petrochemical.

LG Petrochemical Co., Ltd.

Jul. 1992 - Jul. 1992

Pre-Heating, PWHT for the pipe related to SRU K.O. drum installation at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Sep. 1992 – Mar. 1993

PWHT for the TEC/CAPC heater tube at HanKook Fertilizer.

HanKook Fertilizer Co., Ltd.

Jul. 1993 - Dec. 1995

Pre-Heating, PWHT for RFCC project pipe at YeoSu Plant of LG-Caltex.

LG-Caltex Crop.

Sep. 1995 - Nov. 1996

Pre-Heating, PWHT for No.5 CDU project pipe at at UlSan Oil Refinery Plant of SK Corp

ShinHwa Eng. & Const. Co., Ltd.

Dec. 1995 - Dec. 1996

Pre-Heating, PWHT for No.4 CDU and No.2 GO HDS project pipe  at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Dec. 1996 - Sep. 1997

PWHT for Ethylene, BRU pipe at DaeSan Plant of HyunDai Petrochemical.

HyumDai PetroChemical Co., Ltd.

Dec. 1996 - Sep. 1997

PWHT for No.2 Aromatics project pipe at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jan. 1997 - Oct. 1997

PWHT for WCN project pipe at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jan. 1997 - Oct. 1998

PWHT for K/D HDS project pipe at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Oct. 1999 - Feb. 2000 PWHT for #2 BT Extraction project pipe at YeoSu Plant of LG-Caltex. LG-Caltex Corp.
Nov. 1999 - Jul. 2002 PWHT for the pipe in Qatar NODCO Refinery expansion project LG Eng. & Const. Co., Ltd.
Dec. 1999 – Dec. 2002 PWHT for the pipe in Iran South Pars Project Phase #2, #3 on-shore facility construction HyunDai Eng. & Const. Co., Ltd.

1990 - 5. (Pressure) Vessel

Period
Project
Customer
Apr. 1989 – Mar. 1990 Pre-Heating, PWHT for hot stove in Casting furnace at PoHang Steel Mill of POSCO. HyunDai Eng. & Const. Co., Ltd.
May. 1989 - Mar. 1990 Pre-Heating, PWHT for hot stove in #3 blast furnace 5th construction at KwangYang Steel mill of POSCO. HyunDai Eng. & Const. Co., Ltd.

Jan. 1990 - Feb. 1990

PWHT for #3 Coaks plant H2S scrubber tank at KwangYang Steel mill of POSCO.

TaeSung Const. Co., Ltd.

May. 1990 - Jun. 1990

PWHT for the storage tanks at DaeSan Plant of HyunDai Petrochemical.

HyunDai Eng. & Const. Co., Ltd.

May. 1990 – May. 1990

PWHT for the prewash & WTR wash columns at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jun. 1990 - Jun. 1990

PWHT for Kero-Merox unit columns at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jun. 1990 - Jun. 1990

PWHT for the caustic prewash columns at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Sep. 1990 - Sep. 1990

PWHT for the tank nozzle at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jun. 1991 – Nov. 1991

Pre-Heating, PWHT for the stove dome used for #4 blast furnace facilities at KwangYang Steel mill of POSCO.

Hanjung Corp.

Jun. 1991 - Dec. 1991

Pre-Heating in #4 blast furnace 3rd machinery construction at KwangYang Steel mill of POSCO.

HyunDai Eng. & Const. Co., Ltd.

Dec. 1991 – Feb. 1992

Pre-Heating, PWHT for stove dome used for #4 blast furnace at KwangYang Steel mill of POSCO.

Hanjung Corp.

Jul. 1992 - Mar. 1993

PWHT for #1 blast furnace body and cooling plate at PoHang Steel mill of POSCO.

KeoYang Development Co., Ltd.

Nov. 1992 - Mar. 1993

PWHT for Pressure Vessel for GPP project.

LG Electric Wires Co., Ltd.

Dec. 1993 - Mar. 1994

PWHT for tank nozzles at YeoSu Plant of LG-Caltex.

LG-Caltex Corp.

Jan. 1994 - Oct. 1994

Pre-Heating, PWHT in #4 blast furnace 1st repair& maintenance Machinery body construction at PoHang Steel Mill of POSCO.

KeoYang Development Co., Ltd.

May. 1994 – Feb. 1995

Pre-Heating, PWHT in Corex blast furnace 3rd construction at PoHang Steel Mill of POSCO.

KeoYang Development Co., Ltd.

May. 1997 – Aug. 1997

Pre-Heating, PWHT in #2 blast furnace 2nd repair& maintenance construction at PoHang Steel Mill of POSCO.

SamJin Const. Co., Ltd.

Mar. 1997 – Feb. 1998

Pre-Heating, PWHT for #1~#8 unit the turbine shell at Boryung Thermal power plant.

ABB-PE

Sep. 1997 – May. 1998

Pre-Heating, PWHT for #5 blast furnace at PoHang Steel Mill of POSCO.

SamJin Const. Co., Ltd.


1990 - 6. Steel Structures and etc.

Period
Project
Customer

Jul. 1990 – Jul. 1990

PWHT for the filter 3set at YeoSu Plant of LG-Caltex. LG-Caltex Corp.

Aug. 1990 – Aug. 1990

PWHT for the filter at YeoSu Plant of LG-Caltex. LG-Caltex Corp.

Nov. 1990 – Nov. 1990

PWHT for #3 steel manufacturing Electricity Dust Collector at KwangYang Steel Mill of POSCO. POSCO Eng. & Const. Co., Ltd.

Jan. 1991 – Feb. 1991

PWHT for storage tank structure at UlSan Oil Refinery Plant of SK Corp. SK Eng. & Const. Co., Ltd.

Feb. 1993 – Oct. 1994

Pre-Heating, PWHT for steel structure in Company house building construction of POSCO. DongA Eng. & Const. Co., Ltd.

Dec. 1995 – Oct. 1996

Pre-Heating, PWHT for steel structure in DangJin Steel Manufacturing Construction of HanBo Steel Corp. NamKwang E&C Co., Ltd.

Apr. 1998 – Nov. 1999

Pre-Heating, PWHT for steel structure for T/G at #5, #6 YoungKwang Nuclear Power Plant. HyunDai Eng. & Const. Co., Ltd.

1990 - 7. Heat Treatment by Gas Firing method and Dry-out

Period
Project
Customer

Feb. 1990 – Apr. 1990

PWHT for #3 unit Oxygen plant 8,800 BBL ball type oxygen tanks 2set at KwangYang Steel Mill of POSCO. ShinHwa Const. Co., Ltd.

Oct. 1991 – Mar. 1992

PWHT for #4È£±â Oxygen plant ball type gas holders at KwangYang Steel Mill of POSCO. ShinHwa Const. Co., Ltd.

Dec. 1991 – Feb. 1992

PWHT for the spherical tanks at YeoSu plant of HanYang Chem. HanKook Fertilizer Co., Ltd.

Nov. 1993 - Mar. 1994

PWHT for ball type tank at DongYang Nylon Corp. HanKook Fertilizer Co., Ltd.

Dec. 1994 – Dec. 1995.

Heat curing for RFCC project duct and vessel fire-resistant material at YeoSu Plant of LG-Caltex. LG-Caltex Corp

Jan. 1995 – Jun. 1995

PWHT for LL/HDPE B-1 plant polymerization reactor in Iran Tabriz Petro-Chemical Company. ShinHwa Const. Co., Ltd.

Feb. 1996 – Sep. 1996

PWHT for ball type tank at ulsan plant of Taekwang Ind. SangWon Const. Co., Ltd.

Feb. 1996 – Oct. 1996

PWHT for ball type tank in Corex project at DangJin steel mill of HanBo Steel. SangWon Const. Co., Ltd.

Jan. 1997 – Aug. 1997

PWHT for ball type tank in #2 NCC project at DaeSan Complex of HyunDai Petrochemical. SangWon Const. Co., Ltd.

Sep. 1997 – Mar. 1998

PWHT for reactor, crude column, and other vessel (total 7set) in  Jamnagar project. Hanjung Corp.

Oct. 1997 – Nov. 1997

Dry-out for FCC reactor and stripper fire-resistant material in  Jamnagar project. Hanjung Corp.

Jan. 1999 – Jan. 1999

PWHT for C2 splitter in Singapore Olefins project. Hanjung Corp.

Oct. 1998 – Feb. 2000

PWHT for spherical tank (4set) in Mexico Pemex Cadereyta project. Ingenieria Electrica Y Proyectors

1990 - 8. Industry Vesse

Period
Project
Customer

Dec. 1992 – Jun. 1993

Repair& maintenance construction with Heat Treatment for #5-3-5, 500 ton/ch bogie hearth type at Nuclear plant of Hanjung

Hanjung Corp

Nov. 1993 – Mar. 1994

Repair& maintenance construction with Heat Treatment for #5-3-1, 300 ton/ch bogie hearth type at Nuclear plant of Hanjung

Hanjung Corp

Apr. 1994 – Mar. 1995

Remodeling construction with Heating for #2-1-7A, 250 ton/ch bogie hearth type at the plant of Hanjung

Hanjung Corp